Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), announced in the budget 2014-15 envisages feeder separation, strengthening of sub-transmission & distribution network including metering at all levels for the rural areas.
The major components of the scheme are: feeder separation, strengthening of sub-transmission and distribution network, metering at all levels, including input points, feeders and distribution transformers, micro grid and off grid distribution network and rural electrification to complete already sanctioned projects. This scheme will help in round the clock power to rural households and adequate power to agricultural consumers.
Present Status:
No. of Projects Sanctioned | No. of packages | NITs Issued for No. of Pkgs | No. of Pkgs. Awarded |
---|---|---|---|
16 | 73 | 73 | 73 |
Tranche 3
Name of the scheme: Assam Power Sector Enhancement Investment Program, Tranche-3
Source of Fund: Multi-tranche Financing Facility - 1 (MFF-1), Tranche-3 of the Asian Development Bank (ADB)
ADB Loan No: 2800-IND
Loan Amount Sanctioned: 33.3 Million USD
Works under the project: Construction of 29 nos. new 33/11 kV Substations, augmentation of 14 nos. 33/11 kV Substations, Renovation of 4 nos. 33/11 kV Substations, construction of 634. 3km 33 kV lines, 307 km of 11 kV lines, 10 km of 11 kV ABC lines, 93 km of LT ABC lines (HVDS) and 410 nos. DTRs (HVDS) in various districts in Assam.
Estimated Cost of the Project: Rs. 325.17 Crore (ADB Fund: Rs. 226.25 Crore, Counterpart Fund of GOA: Rs. 98.92 Crore)
Status: Under implementation by APDCL through 9 nos. of turnkey contract packages.
Total Contract Value of 9 packages: Rs. 190.09 Crore
Tranche 4
Name of the scheme: Assam Power Sector Enhancement Investment Program, Tranche-4
Source of Fund: Multi-tranche Financing Facility -1 (MFF-1), Tranche-4 of the Asian Development Bank (ADB)
ADB Loan No: MFF-3200 IND
Loan Amount Sanctioned: 50.2 Million USD
Estimated Cost of the Project: Rs. 396.3 Crore (ADB Fund: Rs. 296.75 Crore, Counterpart Fund of GOA: Rs. 99.54 Crore)
Status: Implementation will be started after finalisation of LOA through 4 nos. of turnkey contract packages.
Total Contract Value of 4 packages: Rs. 260.08 Crore
Tranche 2
Name of the scheme: Assam Power Sector Enhancement Investment Program, Tranche-2
Source of Fund: Multi-tranche Financing Facility -2 (MFF-2), Tranche- 2of the Asian Development Bank (ADB)
ADB Loan No: Loan Agreement is Yet to be signed.
Loan Amount Proposed: 48 Million USD
Estimated Cost of the Project: Rs. 341 Crore (ADB Fund: Rs. 275Crore, Counterpart Fund of GOA: Rs. 66 Crore)
Status: Tendering process for 5 nos. of packages is not yet completed.
Total Contract Value of 4 packages: Rs. 242.48 Crore
Sl No | Details of work | Physical Quantity | Cost of the work | Status as on June 2016 |
---|---|---|---|---|
1 | Construction of a new 33/11 kV Substations in various districts all over Assam | 46 nos. (470 MVA) | Rs. 91.49 Crore | 29 nos. completed & charged. Out of the balanced, 10 nos. completed and ready for charging, 6 nos. 80% complete & 1 no. at initial stage. |
2 | Augmentation and R&M of existing 33/11 kV Substations in various districts all over Assam | 29 nos (176 MVA addition) | 27 nos. completed & charged. Balance 2 nos. are 80% complete. | |
3 | Construction of a new 33 kV lines associated with the new Substations | 814 ckm | Rs. 135.49 Crore | 643 ckm completed |
4 | R&M of existing 33 kV lines | 295 ckm | 290 ckm completed | |
5Construction of a new 11 kV lines for power evacuation from the new Substations221 ckm 182 ckm completed | ||||
6 | Installation of new DTRs (250 kVA, 100 kVA & 63 kVA) in various districts all over Assam | 2939 nos (292 MVA) | Rs. 186.98 Crore | Installation of 2939 DTRs (292 MVA) completed |
7 | Extension of 11 kV lines for new DTRs | 609 ckm | 609 ckm complete | |
8 | Extension of LT lines for new DTRs | 195 ckm | 195 ckm complete | |
9 | Construction of dedicated 11 kV Tea Garden feeders | 330 ckm | 330 ckm complete | |
10 | Construction of a new LT ABC line in various districts all over Assam | 516 ckm | Rs. 48..87 Crore | 434 ckm completed |
11 | Conversion of all existing LT lines to LT ABC line in various districts all over Assam | 1103 ckm | 1023 ckm completed | |
12 | Procurement of 33/11 kV Power Transformers (10 MVA & 5 MVA) for new Substations | 136 nos. | 133 nos. procured | |
Total | Rs. 550.59 Crore |
6. Projects under NERSIP (North Eastern Region Power System Improvement Scheme) (World Bank funded)The development objective of North Eastern Region Power System Improvement Project for India is to increase the delivery of electricity at the boundaries of the power distribution network in the participating states in the North Eastern Region.This project has two components:
Status of works under NERPSIP (World Bank) scheme Implementing Agency: PGCIL Amount Sanctioned: Rs. 348.46 CroreAPGCL is in the process of enhancing the Power supply position to meet up the increasing Power demand of the state. Following are the Ongoing & Upcoming ProjectsONGOING PROJECTS : PROJECTS IN PIPELINE :
ACHIEVEMENTS:
Sl No | Details of Work | Physical Quantity | Cost of the work | Status as on June 2016 |
---|---|---|---|---|
1 | Construction of new 33/11 kV, 25 MVA Substation at Thirubari | 1 no.(10 MVA) | Rs. 2.40 Crore | Work in progress. 40% completed |
2 | Construction of a new 33 kV line from Salakati GSS to proposed 33/11 kV Thirubari Substation along with construction of 11 kV feeders for power evacuation. | 16 ckm | Rs. 2.30 Crore | Work in progress.40% completed |
Total | Rs. 4.70 Crore | |||
Sl No. | Details of Work | Physical Quantity | Cost of the work | Status as on June 2016 |
1 | Construction of new 33/11 kV Substations in various districts all over Assam | 12 nos.(160 MVA) | In Tendering process by PGCIL | |
2 | Construction of a new 33/11 KV GIS Substations in Guwahati | 4 nos.(80 MVA) | Land acquisition for the 33/11 kV Substations in progress | |
3 | Construction of a new 33 kV lines(Overhead) associated with the new Substations | 399 ckm | Land for 7 nos. Substations already in possession | |
4 | Construction of new 33 kV underground cable lines with the new GIS Substations at Guwahati | 80 ckm | ||
Total | Rs. 348.46 Crore | |||
Sl. No. | Project Name | Capacity (MW) | Energy Source | Expected Commissioning |
1 | Namrup Replacement Power Project (NRPP) | 100 | Gas | 63 MW Open Cycle: Aug’2016 37 MW Combined Cycle: Mar’2017 |
2 | Lakwa Replacement Power Project (LRPP) | 70 | Gas | March’2018 |
3 | Myntriang Small Hydro Electric Project (MSHEP) | 10.5(St-I=9St-II=1.5) | Hydro | December’2016 |